In Bethanchowk, the water came back

Nine months of construction ended on 9 July 2025 with reliable water access restored for at least sixty households, and a pattern for how HISCUS works in one place over time.

Bethanchowk3 min read

Women handing over a package of supplies across a desk inside a health post office
Handing over supplies to health post staff.

Work on the Bethanchowk water tank started in October 2024 and finished on 9 July 2025. At completion, at least sixty households had reliable water access again.

What makes the project worth reading about is not only the tank. It is the sequence around it.

One community, several visits

On 1 January 2025, while the tank was still under construction, HISCUS delivered support to the Bethanchowk health post. Four weeks later, on 28 January, eighteen women in the same community took part in an Empowering with Dignity session on menstrual health and reusable pad making.

By the time the tank was finished, the organisation had been present in Bethanchowk across three different kinds of work in nine months. The people who would use and maintain the water system already knew who had built it.

Why it holds

Infrastructure that arrives once and leaves does not tend to survive its first repair. Infrastructure planned alongside the health post and the women's sessions belongs to a community that has reason to keep it working.

That is the standard HISCUS applies elsewhere: after the Thapathali floods in October 2024, the response included clothing support for affected children and a community water-storage tank. Again, something durable left behind.

Reported figures

Construction period
October 2024 – 9 July 2025
Households reached
At least 60

Keep reading

View all stories
  • A volunteer cutting pink fabric into reusable pad shapes on the floor of a hall while participants work nearby

    Women & Girls

    Three sessions, sixty-three participants, one method

    Ropeway Sadak, Bethanchowk and Bhaktapur ran months apart in 2025. The format that connects them is deliberately unglamorous: talk, then make something.

    · Ropeway Sadak, Bethanchowk and Bhaktapur

  • A group of Nepali hosts and international visitors wearing marigold garlands outside a building

    Children & Education

    Sarangkot, seven years on

    The Nestling Home was completed in April 2018. In 2025 it supports eleven girls, and two young people who grew up there have moved into higher education and careers.

    · Sarangkot

  • Five people seated around a low table with microphones during a recorded discussion, an organisation banner behind them

    Culture, Environment & Dialogue

    Putting hard subjects on the record

    A gendered-violence roundtable in 2024, a ward waste discussion in 2025, and a run of podcasts. This is the work of not letting a conversation end with the room.

    · Kathmandu Valley